- Same measurement and generation timeline
- Compare time basis, aggregation windows, units and representative locations. IEC 61724-1 defines monitoring-system classes; one sensor does not establish the plant monitoring class.
- Valid and impaired states
- Use the approved verification process to distinguish missing from zero, as well as stale, out-of-range, instrument-fault and lost-communications states.
- Recovery and history
- Local logging and automatic historian import are separate capabilities. Verify timestamps, gaps, duplicates and quality after an approved restart test. A simple communications bridge does not guarantee historical backfill. Compare valid records against expected records in the review period; report invalid and missing records separately.
- Supply and integration responsibilities
- Connect Hive reviews candidate instruments, loggers, enclosures and supply scope against application requirements. The EPC and plant operator control installation, network/PLC/SCADA changes and acceptance tests. This guide is not a compatibility guarantee.
- Factory acceptance (FAT)
- Use simulated signals to check point names, units and scaling before shipment. Review local storage, time basis, missing readings and fault status against the agreed acceptance scope.
- Site acceptance (SAT)
- Under approved test conditions, compare actual sensor, logger, SCADA and historian values and trends at the same times. Confirm communication-loss and recovery behaviour, gaps, duplicates and quality states without changing existing control.